Question: The following project activities are given. If the project manager wants to crash the project by 2 weeks, what will be the minimum cost? Crashing

The following project activities are given. If

The following project activities are given. If the project manager wants to crash the project by 2 weeks, what will be the minimum cost? Crashing Costs Activity Immediate Predecessor Normal Time (weeks) 1st Week 2nd week K 9 $410 L K 2 25 N K 7 275 M LN 4 45 350 J N 3 50 J.M 5 400 400 $400 $90 O $70 O $295 $370