Question: The following represents a project that should be scheduled using CPM: b. What is the critical path? B-E-G-HA-D-G-HA-D-F-HA-C-F-H c. What is the expected project completion

The following represents a project that should be scheduled using CPM: b. What is the critical path? B-E-G-HA-D-G-HA-D-F-HA-C-F-H c. What is the expected project completion time? Note: Do not round intermediate calculations. Round your answer to 3 decimal places. d. What is the probability of completing this project within 23 days? Note: Use Excel's NORM.S.DIST function to find the correct probability for your computed Z value. Do not round intermediate calculations. Round Z value to 2 decimal places and final answer to 4 decimal places. The following represents a project that should be scheduled using CPM: b. What is the critical path? B-E-G-HA-D-G-HA-D-F-HA-C-F-H c. What is the expected project completion time? Note: Do not round intermediate calculations. Round your answer to 3 decimal places. d. What is the probability of completing this project within 23 days? Note: Use Excel's NORM.S.DIST function to find the correct probability for your computed Z value. Do not round intermediate calculations. Round Z value to 2 decimal places and final answer to 4 decimal places
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts