Question: The following represents a project that should be scheduled using CPM: Use Appendix G. b. What is the critical path? A-D.G-H A.C-F-H B-E-G-H A-D-F-H c.
The following represents a project that should be scheduled using CPM: Use Appendix G. b. What is the critical path? A-D.G-H A.C-F-H B-E-G-H A-D-F-H c. What is the expected project completion time? (Do not round intermediate calculations. Round your answer to 3 decimal places.) d. What is the probability of completing this project within 20 days? (Use Excel's