Question: The following represents a project that should be scheduled using CPM: IMMEDIATE PREDECESSORS TIMES ( DAYS ) a ACTIVITY ABCDEFGH A 1 m b 4

The following represents a project that should be scheduled using CPM:
IMMEDIATE PREDECESSORS
TIMES (DAYS)
a
ACTIVITY
ABCDEFGH
A
1
m
b
4
7
3
5
826236
2
5
2
11
A
1
9
B
1
3
C,D
1
11
G
D, E
1
3
F,G
2
2
3
b. What is the critical path?
OA-D-G-H
OB-E-G-H
A-D-F-H
OA-C-F-H
c. What is the expected project completion time?
Note: Do not round intermediate calculations. Round your answer to 3 decimal places.
Project completion time
days

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!