Question: The following represents a project that should be scheduled using CPM: IMMEDIATE PREDECESSORS TIMES ( DAYS ) a ACTIVITY ABCDEFGH A 1 m b 4
The following represents a project that should be scheduled using CPM:
IMMEDIATE PREDECESSORS
TIMES DAYS
a
ACTIVITY
ABCDEFGH
A
m
b
A
B
CD
G
D E
FG
b What is the critical path?
OADGH
OBEGH
ADFH
OACFH
c What is the expected project completion time?
Note: Do not round intermediate calculations. Round your answer to decimal places.
Project completion time
days
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
