The following represents a project that should be scheduled using CPM:

1) What is the critical path?
A-C-F-H
B-E-G-H
A-D-F-H
A-D-G-H
2) What is the expected project completion time? (Do not round intermediate calculations. Round your answer to 3 decimal places.
3) What is the probability of completing this project within 22 days? (Use Excel's NORMSDIST() function to find the correct probability for your computed Z-value. Do not round intermediate calculations. Round "z" value to 2 decimal places and final answer to 4 decimal places.)
TIMES (DAYS) IMMEDIATE