Question: The following represents a project that should be scheduled using CPM: ACTIVITYIMMEDIATE PREDECESSORSTIMES ( DAYS ) ambA 1 5 9 B 1 2 3 CA

The following represents a project that should be scheduled using CPM:
ACTIVITYIMMEDIATE PREDECESSORSTIMES (DAYS)ambA159B123CA357DA1410EB123FC,D1212GD,E168HF,G238
What is the critical path?
multiple choice
A-C-F-H
B-E-G-H
A-D-G-H
A-D-F-H
What is the expected project completion time?
Note: Do not round intermediate calculations. Round your answer to 3 decimal places.