Question: The following represents a project that should be scheduled using CPM: ACTIVITYIMMEDIATE PREDECESSORSTIMES ( DAYS ) ambA 1 5 9 B 1 2 3 CA
The following represents a project that should be scheduled using CPM:
ACTIVITYIMMEDIATE PREDECESSORSTIMES DAYSambABCADAEBFCDGDEHFG
What is the critical path?
multiple choice
ACFH
BEGH
ADGH
ADFH
What is the expected project completion time?
Note: Do not round intermediate calculations. Round your answer to decimal places.