Question: The following represents a project that should be scheduled using CPM: IMMEDIATE ACTIVITY PREDECESSORS A B C D A E B F C,D G DE

The following represents a project that should be

The following represents a project that should be scheduled using CPM: IMMEDIATE ACTIVITY PREDECESSORS A B C D A E B F C,D G DE H F,G TIMES (DAYS) a m b 1 4 7 1 6 11 2 6 7 3 2 13 1 2 6 1 5 9 1 2 9 3 6 9 b. What is the critical path? A-D-G-H A-C-F-H A-D-F-H B-E-G-H c. What is the expected project completion time? (Do not round intermediate calculations. Round your answer to 3 decima Project completion time days