Question: The following represents a project that should be scheduled using CPM: IMMEDIATE PREDECESSORS TIMES (DAYS) ACTIVITY a m b A 1 4 7 B 2

The following represents a project that should be scheduled using CPM:

IMMEDIATE PREDECESSORS TIMES (DAYS)
ACTIVITY a m b
A 1 4 7
B 2 3 7
C A 3 5 7
D A 5 6 10
E B 1 2 6
F C,D 1 3 6
G D,E 1 3 14
H F,G 2 5 14

b. What is the critical path?

A-C-F-H
B-E-G-H
A-D-F-H
A-D-G-H

c. What is the expected project completion time? (Round your answer to 3 decimal places.)

Project completion time days

d. What is the probability of completing this project within 22 days? (Do not round intermediate calculations. Round your answer to 4 decimal places.)

Probability

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!