Question: The following represents a project that should be scheduled using CPM: IMMEDIATE ACTIVITY PREDECESSORS B D E B F C,D G D, E H F,G

The following represents a project that should be
The following represents a project that should be scheduled using CPM: IMMEDIATE ACTIVITY PREDECESSORS B D E B F C,D G D, E H F,G TIMES (DAYS) a b 14 7 3 5 10 2 5 8 4 6 11 1 2 3 3 5 7 1 2 6 2 5 6 b. What is the critical path? A-D-G-H A-C-F-H B-E-G-H A-D-F-H c. What is the expected project completion time? (Do not round intermediate calculations. Round your answer to 3 decimal places.) Project completion time days