Question: The following represents a project that should be scheduled using CPM: IMEDIATE ACTIVITY PREDECESSORS D E TIMES (DAYS) a m b 1 2 3 7

The following represents a project that should be
The following represents a project that should be scheduled using CPM: IMEDIATE ACTIVITY PREDECESSORS D E TIMES (DAYS) a m b 1 2 3 7 28 11 1 5 1 2 3 1 4 7 1 2 3 2 3 G CD D. F G b. What is the critical path? OBE-G-H AD-GH O ACEH A-D-FH c. What is the expected project completion time? (Do not round intermediate calculations, Round your answer to 3 decimal places.) Project completion time any