Question: The following represents a project that should be scheduled using CPM: IMMEDIATE PREDECESSORS TIMES (DAYS) ACTIVITY a m b A 1 5 9 B 1

The following represents a project that should be scheduled using CPM:

IMMEDIATE PREDECESSORS TIMES (DAYS)
ACTIVITY a m b
A 1 5 9
B 1 2 3
C A 3 5 7
D A 1 4 10
E B 1 2 3
F C,D 1 2 12
G D,E 1 6 8
H F,G 2 3 8

b. What is the critical path?

A-C-F-H

B-E-G-H

A-D-G-H. Correct answer

A-D-F-H

c. What is the expected project completion time? (Do not round intermediate calculations. Round your answer to 3 decimal places.)

18.667 correct answer

d. What is the probability of completing this project within 20 days? (Use Excel's NORM.S.DIST() function to find the correct probability for your computed Z-value. Do not round intermediate calculations. Round "z" value to 2 decimal places and final answer to 4 decimal places.)

Need help solving this

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!