Question: The following represents a project that should be scheduled using CPM: IMMEDIATE ACTIVITY PREDECESSORS A i B D E F G H A A B

The following represents a project that should be

The following represents a project that should be

The following represents a project that should be scheduled using CPM: IMMEDIATE ACTIVITY PREDECESSORS A i B D E F G H A A B C,D DE F,G TIMES (DAYS) a b 1 8 1 2 9 2 7 1 2 12 1 2 3 1 3 5 1 7 13 2 5 13 n d. What is the probability of completing this project within 20 days? (Use Excel's NORM.S.DIST() function to find the correct probability for your computed 2-value. Do not round intermediate calculations. Round "z" value to 2 decimal places and final answer to 4 decimal places.) Probability