Question: The following represents a project that should be scheduled using CPM: IMMEDIATE PREDECESSORS TIMES (DAYS) ACTIVITY a m b A 1 4 7 B 1
The following represents a project that should be scheduled using CPM: IMMEDIATE PREDECESSORS TIMES (DAYS) ACTIVITY a m b A 1 4 7 B 1 6 11 C A 2 6 7 D A 3 2 13 E B 1 2 6 F C,D 1 5 9 G D,E 1 2 9 H F,G 3 6 9
b. What is the critical path? multiple choice A-D-F-H B-E-G-H A-D-G-H A-C-F-H Correct
c. What is the expected project completion time? (Do not round intermediate calculations. Round your answer to 3 decimal places.)