Question: The following represents a project that should be scheduled using CPM: b. What is the critical path? A-C-F-H A-D-F-H A-D-G-H B-E-G-H c. What is the

The following represents a project that should be scheduled using CPM: b. What is the critical path? A-C-F-H A-D-F-H A-D-G-H B-E-G-H c. What is the expected project completion time? (Round your answer to 3 decimal places.) Project completion time days d. What is the probability of completing this project within 16 days? (Do not round intermediate calculations. Round your answer to 4 decimal places.) Probability
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts