Question: The following represents a project that shouldbe scheduled using CPM: Time (DAYS) Activity Immediate Predecessors a m b A - 1 1 4 B -
The following represents a project that shouldbe scheduled using CPM: Time (DAYS) Activity Immediate Predecessors a m b A - 1 1 4 B - 4 5 6 C A 3 7 1 D A 1 2 9 E B 1 6 8 F C, D 1 2 12 G D, E 2 3 10 H F, G 2 3 10 a. What is the critical path? b. what is the expected project completion time? d. What is the probability of completing this project within 19 days? Any and all help will be quite helpful. Thanks in advance