Question: The following represents a project that shouldbe scheduled using CPM: Time (DAYS) Activity Immediate Predecessors a m b A - 1 1 4 B -

The following represents a project that shouldbe scheduled using CPM: Time (DAYS) Activity Immediate Predecessors a m b A - 1 1 4 B - 4 5 6 C A 3 7 1 D A 1 2 9 E B 1 6 8 F C, D 1 2 12 G D, E 2 3 10 H F, G 2 3 10 a. What is the critical path? b. what is the expected project completion time? d. What is the probability of completing this project within 19 days? Any and all help will be quite helpful. Thanks in advance

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!