Question: The following standards for variable overhead have been established for a company that makes only one product: Standard hours per unit of output 4.7 hours
The following standards for variable overhead have been established for a company that makes only one product:
| Standard hours per unit of output | 4.7 | hours |
| Standard variable overhead rate | $16.00 | per hour |
|
| ||
| The following data pertain to operations for the last month: |
| Actual hours | 8,400 | hours |
| Actual total variable overhead cost | $125,020 | |
| Actual output | 1,770 | units |
|
| ||
| Required: | |
| a. | What is the variable overhead rate variance for the month? (Input the amount as a positive value. Leave no cells blank - be certain to enter "0" wherever required. Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance.) |
| b. | What is the variable overhead efficiency variance for the month? (Input the amount as a positive value. Leave no cells blank - be certain to enter "0" wherever required. Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance.) |