Question: The following standards have been established for a raw material used to make product O84: Standard quantity of the material per unit of output 7.5
The following standards have been established for a raw material used to make product O84:
| Standard quantity of the material per unit of output | 7.5 | meters | |
| Standard price of the material | $ | 18.70 | per meter |
The following data pertain to a recent month's operations:
| Actual material purchased | 3,800 | meters | |
| Actual cost of material purchased | $ | 74,480 | |
| Actual material used in production | 3,500 | meters | |
| Actual output | 540 | units of product O84 | |
The direct materials purchases variance is computed when the materials are purchased.
Required:
a. What is the materials price variance for the month?
b. What is the materials quantity variance for the month?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock