Question: The following steps should be followed when setting up project (business office) with Project Libre. Set the basic project information Open Project Libre - Click
The following steps should be followed when setting up project (business office) with Project Libre.
- Set the basic project information
- Open Project Libre - Click Create Project.
- Enter New Project Name, manger, start date, press ok.
- Click on File (top left), select calendar and give name
- Save as and enter the file name as (your name) cp1. For example, SmithJanecp1.mpp.
- Click on the Project Name area and add project task.
- Enter Start and Finish Dates
- Select information the task and set if fix date
- Add other task Click on OK.
- Add your durations for each task
- Set basic Gantt chart format and select your relationships (use also for tracking Gantt chart view).
- Select relationships with task that are related
- Select a lag if necessary
- Set your task dependency by double clicking on the relationship bar.
- Click on OK.
- Make sure to save your information
- Next steps will be to set up resources.
Building a Network Diagram
The first step in building the network diagram is sequencing all of the activities. A completed network diagram enables you to able to determine: (1) a project's scheduled completion time, (2) the slack or float of project activities, and (3) the critical path of your project.
Build a Project Network (or a Partial Network)
- Brainstorm the activities required to complete the work packages. Record on note cards or Post-it notes. Don't worry about the order or sequence.
- Sequence the note cards or Post-it notes with the activities. Determine:
- The order of activities
- Which activities can occur in parallel
- Which activities require dependencies
- Mandatory: before the activity can begin or end the completion of another task is required.
- Discretionary: a best practice or convenience. However, the subsequent task can begin if the discretionary dependency is not completed.
- External: requires additional project or process, such as permits.
- Internal: dependencies within the control of the project team.
- Place the notes on a wall based steps 1 and 2.
- Build a network based on step.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock