Question: The following steps should be followed when setting up project (business office) with Project Libre. Set the basic project information Open Project Libre - Click

The following steps should be followed when setting up project (business office) with Project Libre.

  1. Set the basic project information
    • Open Project Libre - Click Create Project.
    • Enter New Project Name, manger, start date, press ok.
    • Click on File (top left), select calendar and give name
    • Save as and enter the file name as (your name) cp1. For example, SmithJanecp1.mpp.
    • Click on the Project Name area and add project task.
    • Enter Start and Finish Dates
    • Select information the task and set if fix date
    • Add other task Click on OK.
    • Add your durations for each task
  2. Set basic Gantt chart format and select your relationships (use also for tracking Gantt chart view).
    • Select relationships with task that are related
    • Select a lag if necessary
    • Set your task dependency by double clicking on the relationship bar.
    • Click on OK.
  3. Make sure to save your information
    • Next steps will be to set up resources.

Building a Network Diagram

The first step in building the network diagram is sequencing all of the activities. A completed network diagram enables you to able to determine: (1) a project's scheduled completion time, (2) the slack or float of project activities, and (3) the critical path of your project.

Build a Project Network (or a Partial Network)

  1. Brainstorm the activities required to complete the work packages. Record on note cards or Post-it notes. Don't worry about the order or sequence.
  2. Sequence the note cards or Post-it notes with the activities. Determine:
    • The order of activities
    • Which activities can occur in parallel
    • Which activities require dependencies
    • Mandatory: before the activity can begin or end the completion of another task is required.
    • Discretionary: a best practice or convenience. However, the subsequent task can begin if the discretionary dependency is not completed.
    • External: requires additional project or process, such as permits.
    • Internal: dependencies within the control of the project team.
  3. Place the notes on a wall based steps 1 and 2.
  4. Build a network based on step.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!