Question: The following summary data for Amirkhani Construction Co.'s (ACC) relates to Job 1227, which was completed in 2019, are presented below to answer question 16:
The following summary data for Amirkhani Construction Co.'s (ACC) relates to Job 1227, which was completed in 2019, are presented below to answer question 16:
Bid price $450,000
Original estimated contract cost:
2018 $180,000
2019 195,000
Gross profit $75,000
Actual cost incurred in:
2018 $180,000
2019 $200,000
Assuming ACC recognizes revenue over time according to percentage of completion for this contract, the gross profit recognized in 2019 would be (rounded to the nearest thousand):
a. $70,000.
b. $36,000.
c. $34,000.
d. $75,000.