Question: The following table gives the processing times and due dates for five jobs which are to be processed on a machine. Assign the jobs according

The following table gives the processing times
The following table gives the processing times and due dates for five jobs which are to be processed on a machine. Assign the jobs according to the shortest processing time (SPT). PROCESSING JOB TIME 101 8 days 102 9 days 1036 days 104 11 days 105 7 days DUE DATE (DAYS HENCE) 5 3 Calculate the average flow time using a job order based on SPT. (Round your answer to 1 decimal place.) Answer is complete but not entirely correct. Mean low 16.6 days