Question: The following table includes activities, their durations for both normal and crash time as well as the associated costs. Activity Predecessor Normal Duration Normal Cost

The following table includes activities, their durations for both normal and crash time as well as the associated costs.
Activity Predecessor Normal Duration Normal Cost Crash time Crash cost
A -61006100
B -82008200
C A 42002800
D B,C 9200054500
E B 950042000
F E 10150063500
G C 880052000 What is the duration of the project under normal conditions?