Question: The following table is an activity list that includes the duration and predecessor for a series of project activities. What is the duration of the

 

The following table is an activity list that includes the duration and predecessor for a series of project activities.

What is the duration of the critical path (in weeks)?

ActivityDuration (weeks)Predecessor
A2START
B4A, E
C6A
D3B, C
E7START
F2E
END-D ,F

Question 2

Consider the project described in question 1.

What is the total slack for activity B, assuming the project is finished in its minimum duration?

Question 3

Consider the project described in question 1.

Suppose the project is set to be completed in 18 weeks. What is the total slack for activity A (in weeks)?

(individually)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

It looks like theres an issue with the project structuretheres no explicit START node in the table p... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!