Question: The following table is an activity list that includes the duration and predecessor for a series of project activities. What is the duration of the
The following table is an activity list that includes the duration and predecessor for a series of project activities.
What is the duration of the critical path (in weeks)?
| Activity | Duration (weeks) | Predecessor |
| A | 2 | START |
| B | 4 | A, E |
| C | 6 | A |
| D | 3 | B, C |
| E | 7 | START |
| F | 2 | E |
| END | - | D ,F |
Question 2
Consider the project described in question 1.
What is the total slack for activity B, assuming the project is finished in its minimum duration?
Question 3
Consider the project described in question 1.
Suppose the project is set to be completed in 18 weeks. What is the total slack for activity A (in weeks)?
Step by Step Solution
There are 3 Steps involved in it
It looks like theres an issue with the project structuretheres no explicit START node in the table p... View full answer
Get step-by-step solutions from verified subject matter experts