Question: The following table is an activity list that includes the duration and predecessor for a series of project activities. What is the duration of the

The following table is an activity list that includes the duration and predecessor for a series of project activities.
What is the duration of the critical path (in weeks)?
Activity Duration (weeks) Predecessor
A 2 START
B 4 A, E
C 6 A
D 3 B, C
E 7 START
F 2 E
END - D ,F
Question 2
Consider the project described in question 1.
What is the total slack for activity B, assuming the project is finished in its minimum duration?
Question 3
Consider the project described in question 1.
Suppose the project is set to be completed in 18 weeks. What is the total slack for activity A (in weeks)?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!