Question: The following table list the components needed to assemble an end item, lead times and quantities on hand. a. if 19 units of the end
The following table list the components needed to assemble an end item, lead times and quantities on hand.
The following table lists the components needed to assemble an end item, lead times, and quantities on hand Item LT (wk) Amount on hand E (2) F(3) G2) a. If 19 units of the end item are to be assembled, how many additional units of E are needed? (Hint. You don't need to develop an MRI plan to determine this) Additional units b. An order for the end item is scheduled to be shipped at the start of week 17. What is the latest week that the order can be started and still be ready to ship on time? (Hint You don't need to develop an MRP plan for this part either) The latest week a. if 19 units of the end item are to be assembled, how many additional units of ER needed?
b. In order for the end item is scheduled to be shipped at the end of week 17. What is the latest week that the order can be started and still be ready to ship on time?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock