Question: The following table lists the activity time estimates ( in weeks ) for each activity. table [ [ Activity , Optimistic,Most Probable,Pessimistic ] ,

The following table lists the activity time estimates (in weeks) for each activity.
\table[[Activity,Optimistic,Most Probable,Pessimistic],[A,4,5,6],[B,2.5,3,3.5],[C,5,6,7],[D,5,5.5,9],[E,5,7,9],[F,2,3,4],[G,7,9,11],[H,7,8,15]]
Based only on the critical path, what is the estimated probability that the project will be completed within the given time frame? (Round your answers to four
(a) Within 21 weeks?
(b) Within 23 weeks?
(c) Within 27 weeks?
 The following table lists the activity time estimates (in weeks) for