Question: The following table lists the components needed to assemble an end item, lead times ( in weeks ) , and quantities on hand.Chapter Thirteen MRP
The following table lists the components needed to assemble an end item, lead times in weeks and quantities on hand.Chapter Thirteen MRP and ERP
The following table lists the components needed to assemble an end item, lead times in weeks
and quantities on hand.
a If units of the end item are to be assembled, how many additional units of are needed?
Hint: You don't need to develop an MRP plan.
b An order for the end item is scheduled to be shipped at the start of week What is the latest
week that the order can be started and still be ready to ship on time? Hint: You don't need to
develop an MRP plan.
Eighty units of end item are needed at the beginning of week Three cases units per case of
have been ordered and one case is scheduled to arrive in week one in week and one in week
Note: must be ordered by the case, and must be produced in multiples of units. There are units
of B and units of now on hand. Lead times are two weeks each for E and B and one week for J
a Prepare a material requirements plan for component
b Suppose that in week the quantity of needed is changed from to The plannedorder releases
through week have all been executed. How many more Bs and Js will be on hand in week
a One hundred twenty units of end item are needed at the beginning of week Prepare a mate
rial requirements plan for component Take into account that on hand there are units of
units of A units of B and units of C Also, there is a scheduled receipt of units of
component in week Lead times are two weeks for and and one week for the other com
ponents. Lotforlot ordering will be used for all items.
b Ninetyfive units of end item E are needed at the beginning of week Prepare a material require
ments plan for component Take into account that units of are currently on hand, as well as
units of B units of C and units of D Also, units of C have been outsourced and are
expected to arrive in week Lead times are two weeks for E and C and one week for the other
components. Assume lotforlot ordering except for where multiples of must be used.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
