Question: The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item Lead Time Amount Direct
| The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. | |||||||||||||||
| Item | Lead Time | Amount | Direct Components | ||||||||||||
| on Hand | |||||||||||||||
| End | 1 | 0 | L(2), C(1), K(3) | ||||||||||||
| L | 1 | 8 | B(2), J(3) | ||||||||||||
| C | 2 | 16 | G(2), B(2) | ||||||||||||
| K | 3 | 21 | H(4), B(3) | ||||||||||||
| B | 2 | 33 | |||||||||||||
| J | 1 | 26 | |||||||||||||
| G | 2 | 6 | |||||||||||||
| H | 2 | 0 | |||||||||||||
| a. If 50 units of the end item are to be assembled, how many additional units of B are needed? (50 Points) | |||||||||||||||
| b. An order for the end item is scheduled to be shipped at the start of week 9. What is the latest week that the order can be started and still be ready to ship on time? (50 Points) | |||||||||||||||
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock