Question: The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item Lead Time Amount on
The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand.
| Item | Lead Time | Amount on Hand | Direct Components |
| End | 1 | - | L(2), C(1), K(3) |
| L | 2 | 10 | B(2), J(3) |
| C | 3 | 15 | G(2), B(2) |
| K | 3 | 20 | H(4), B(2) |
| B | 2 | 30 | |
| J | 3 | 30 | |
| G | 3 | 5 | |
| H | 2 | 0 |
a) If 45 units of the End item are to be assembled, additional units of item B will be needed. (Hint: You dont need to develop an MRP plan, but you WILL NEED to create a product structure tree)
b) An order for the end item is scheduled to be shipped at the start of week 8. Week # is the latest week that the order can be started and still be ready to ship on time? (Hint: You don't need to develop an MRP plan for this part either. You can create an assembly time chart by drawing your product structure tree sideways)