Question: The following table lists the components needed to assemble an end item, the manufacturing or purchase lead times (in weeks) for typical lot sizes, amount
The following table lists the components needed to assemble an end item, the manufacturing or purchase lead times (in weeks) for typical lot sizes, amount on hand, and the direct components of each item and, in brackets, the number of each component for each parent.
| Item | Lead Time | Amount on Hand | Direct Components | |
| End item | 1 | - | L(2), C(1), K(3) | |
| L | 1 | 8 | B(2), J(3) | |
| C | 2 | 14 | G(2), B(2) | |
| K | 2 | 22 | H(4), B(2) | |
| B | 4 | 26 | ||
| J | 2 | 32 | ||
| G | 4 | 7 | ||
| H | 3 | - | ||
a. This part of the question is not part of your Connect assignment. b. If 54 units of the end item are to be assembled, how many additional units of B are needed? (You dont need to develop the MRP tables.) Additional units c. An order for 54 units of the end item is scheduled to be shipped at the start of week 8. What is the latest week that the components of the order can be started and the order still be ready to ship on time? (You dont need to develop the MRP tables.) The latest week