Question: The following table lists the components needed to assemble an end item, lead times ( in weeks ) , and quantities on hand. ItemLead TimeAmount
The following table lists the components needed to assemble an end item, lead times in weeks and quantities on hand.
ItemLead TimeAmount on HandDirect ComponentsEndL C KLB JCG BKH BBJGH
Click here for the Excel Data File
If units of the end item are to be assembled, how many additional units of B are needed? Hint: You dont need to develop an MRP plan.
An order for the end item is scheduled to be shipped at the start of week What is the latest week that the order can be started and still be ready to ship on time? Hint: You dont need to develop an MRP plan.
The following table lists the components needed to assemble an end item, lead times in weeks and quantities on hand.
Click here for the Excel Data File
a If units of the end item are to be assembled, how many additional units of B are needed? Hint You don't need to develop an MRP plan.
Answer is complete but not entirely correct.
Additional units
b An order for the end item is scheduled to be shipped at the start of week What is the latest week that the order can be started and still be ready to ship on time? Hint You don't need to develop an MRP plan.
Answer is complete but not entirely correct.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock