Question: The following table lists the required processing times and setup times at each of the steps. Assume that the unit of production is a wafer,

The following table lists the required processing times and setup times at each of the steps. Assume that the unit of production is a wafer, from which individual chips are cut at a later stage.
Note: A setup can only begin once the batch has arrived at the machine.
Process Step 1 Depositing 2 Patterning 3 Etching
Setup time 47 min. 33 min. 23 min.
Processing time 0.17 min./unit 0.27 min./unit 0.22 min./unit
(a) What is the process capacity in units per hour with a batch size of 100 wafers? (Round your final answer to the nearest whole number.)