Question: The following table provides the normal and crash time (in weeks) for a project as well as the crash cost per week for the 4
The following table provides the normal and crash time (in weeks) for a project as well as the crash cost per week for the 4 project activities. The precedence relationships for the activities are provided in the network model.
Activity Normal Time Crash Time Crash Cost / week ($)
A 4 2 4000
B 5 2 2000
C 4 3 2000
D 2 1 3000
Project newtworkProject starts with Activity A; B and C follow A; D is done after B and C;
Type your answers for the following 3 questions in the box below. Use capital letters and no spaces. Example: ABC
The normal critical path is:
a. A-C-D
b. A-D
c. A-B-D
d. B-D
The normal project duration is:
a. 5 weeks
b. 6 weeks
c. 10 weeks
d. 11 weeks
The best choice for an activity to be crashed in order to reduce the project duration by one week would be:
a. A
b. B
c. C
d. D