Question: The following table represents a plan for a project: JOB NUMBER PREDECESSOR JOB ( S ) TIMES ( DAYS ) a m b 1 2
The following table represents a plan for a project:
JOB NUMBER PREDECESSOR JOBS TIMES DAYS
a m b
awhat is the expected completion time for the project? b What is the probability that the project will take more than days to complete?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
