Question: The following table represents the requirements for manufacturing a commodity for nine activities. Find the critical path and time for the manufacture of this commodity

The following table represents the requirements for manufacturing a commodity for nine activities. Find the critical path and time for the manufacture of this commodity
The following table represents the requirements
Activity A-B B-C B-D C-D C-E C-F D-E D-F E-F Dij 4 4 2 0 3 4 6 5 7