Question: The following table shows orders to be processed at a machine shop. Processing times are in days. Due is the number of date left until
The following table shows orders to be processed at a machine shop. Processing times are in
days. Due is the number of date left until Due date. Jobs are listed in order of arrival.
a Determine the processing sequence using SPTShortest Processing Time first
CAEBD
b What is the average tardiness by SPT days
c Determine the processing sequence using EDDEarliest Due Date first
DBACE
d What is the average tardiness by EDD? days