The following table shows the information on a marketing project .It is currently at the end of
Fantastic news! We've Found the answer you've been seeking!
Question:
- The following table shows the information on a marketing project .It is currently at the end of day 48.
- Determine if the project is in control based on time and cost to date.
- If not, what is the cost of over age or underage?
Can you please explain the math step by step
Activity | Duration | Budget | ActualCost | % Complete |
1-2 | 10 | 300 | 250 | 100.00 |
2-3 | 8 | 400 | 450 | 100.00 |
2-4 | 12 | 350 | 380 | 100.00 |
3-5 | 18 | 405 | 400 | 70.00 |
5-6 | 16 | 450 | ------- | 0.00 |