The following table shows the precedence relationships among the activities needed to be completed for an office
Fantastic news! We've Found the answer you've been seeking!
Question:
The following table shows the precedence relationships among the activities needed to be completed for an office renovation project as well as estimated optimistic, most likely, and pessimistic times (in days for each activity)
Identify ann paths that the project has and calculate the mean and standard deviation for each path. (SHOW ALL WORK )
Calculate the probability of the renovation being completed in 25 days based on the critical path
ACTIVITY | PREDECESSORS | OPTIMISTIC | MOST LIKELY | PESSIMISTIC |
A | - | 2 | 4 | 6 |
B | - | 3 | 8 | 10 |
C | A | 7 | 9 | 14 |
D | B | 5 | 8 | 11 |
E | C,D | 4 | 5 | 6 |
F | B | 8 | 10 | 15 |
G | E,F | 4 | 6 | 8 |