Question: The following table shows the timetable for the two projects for projects A and B and the installation of an existing project in Year 0.
The following table shows the timetable for the two projects for projects A and B and the installation of an existing project in Year 0. The interest rate (cost of capital) equals 9.5%. Answer the following questions: Which of the two projects will you accept, the two projects will be rejected based on the assumption that you want to recover your money within 3 years of the life of the project? Why? (2 tag) B. Calculate the profitability index for the two projects? The two projects are based on the profitability index If the two projects are mutually exclusive, and why? (3 mark