Question: The following time estimates are given for an activity: optimistic time = 16 days, most likely time = 24 days and pessimistic time = 38
The following time estimates are given for an activity: optimistic time = 16 days, most likely time = 24 days and pessimistic time = 38 days.
What is the expected time to complete this activity?
Group of answer choices
A. 16
B. 24
C. 38
D. 25
E. None of these answers are correct