Question: The function point count for a software project was calculated to be 1080. a) Historical data for projects of this type indicates that six function

The function point count for a software project was calculated to be 1080.

a) Historical data for projects of this type indicates that six function points equals one person month. Assume that for this project it is possible for five people to work productively on the project simultaneously. What is the minimum estimated project duration for this project? Show all your working and explain each of the steps involved in calculating the minimum duration.

b) If the project must be completed in 12 months, what is the minimum number of people that will be needed for this project? You must explain your working.

c) In part (b) you calculated the minimum number of people to complete the project in 12 months. Explain why it is unlikely that you will be able to achieve the 12 month deadline with the number of workers you calculated in part (b).

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!