Question: The Gantt chart never shows: a . WBS elements b . Sequencing relations c . Start and finish dates of the activities d . Human

The Gantt chart never shows:
a. WBS elements
b. Sequencing relations
c. Start and finish dates of the activities
d. Human resource hourly rates