Question: The Gantt chart never shows: a . WBS elements b . Sequencing relations c . Start and finish dates of the activities d . Human
The Gantt chart never shows:
a WBS elements
b Sequencing relations
c Start and finish dates of the activities
d Human resource hourly rates