Question: The highest level of work breakdown structure is the: Select one: A . Subdeliverable. B . Work package. C . Deliverable. D . Project.
The highest level of work breakdown structure is the:
Select one:
A Subdeliverable.
B Work package.
C Deliverable.
D Project.