Question: The Implement Risk Responses process involves implementing the agreed - upon risk response plans. All of the following options are true regarding this process except
The Implement Risk Responses process involves implementing the agreedupon risk response plans.
All of the following options are true regarding this process except which one?
Select one
The response plan isn't of much value if no one is monitoring risk symptoms and triggers and taking action to
A
manage the risks before they occur.
B The outputs of this process are change requests and project documents updates.
O c The tools and techniques of this process are expert judgment, interpersonal and team skills, and PMIS.
D The project manager is responsible for implementing risk response plans.