Question: The Independent System Operator (ISO) will use an economic dispatch curve to: Group of answer choices Decide which power plants to build Identify the lowest
The Independent System Operator (ISO) will use an economic dispatch curve to: Group of answer choices Decide which power plants to build Identify the lowest cost collection of electric generators to meet the electricity demand Identify the required maximum generation capacity for the next year