Question: The indirect costs for each duration are $ 1 , 5 0 0 for 1 7 weeks, $ 1 , 4 5 0 for 1

The indirect costs for each duration are $1,500 for 17 weeks, $1,450 for 16 weeks, $1,400 for 15 weeks, $1,350 for 14 weeks, $1,300 for 13 weeks, $1,250 for 12 weeks, $1,200 for 11 weeks, and $1,150 for 10 weeks.