Question: The information below is about a component used in producing laser printers. The initial on-hand inventory is 80 and the supplier lead time is 3
The information below is about a component used in producing laser printers. The initial on-hand inventory is 80 and the supplier lead time is 3 weeks. Using a lot-for-lot rule with Q =100, complete the MRP record (table below) for the component. Explain what the result tellsthe inventory analyst to do.
Weeks 1 2 3 4 5 6 7 8 Gross Requirement 20 0 60 0 100 80 0 60 Scheduled Receipts 100 Projected On-Hand 80 Planned Receipts Planned Order Release