Question: The information needed to develop a master production schedule will be got from: Group of answer choices the production plan None of these inventory levels
The information needed to develop a master production schedule will be got from:
Group of answer choices
the production plan
None of these
inventory levels for individual end items
All of these
the forecast of individual end items
Step by Step Solution