Question: The information-gathering techniques used in the risk identification process include all of the following except _____________. A. Root Cause Identification B. Delphi Technique C. SWOT
The information-gathering techniques used in the risk identification process include all of the following except _____________.
| A. | Root Cause Identification | |
| B. | Delphi Technique | |
| C. | SWOT Analysis | |
| D. | Checklist Analysis |
A risk response strategy that generally reduces the probability or impact of the event without altering the project's objectives is called:
| A. | Avoidance | |
| B. | Acceptance | |
| C. | Mitigation | |
| D. | Transfer |