Question: The initial step in the risk management process is to Group of answer choices Set aside budget funds for managing the risks. Appoint a risk

The initial step in the risk management process is to
Group of answer choices
Set aside budget funds for managing the risks.
Appoint a risk manager.
Assess the risk potential.
Determine the level of acceptable risk.
Identify the risks.