Question: The _ _ _ _ _ _ _ _ is a portion of the project plan detailing the activities, their schedules, and resources, including personnel.
The is a portion of the project plan detailing the activities, their schedules, and resources, including personnel. a Risk management plan
b Quality management plan
c Action plan
d Procurement plan